From red-rated CDM audit to zero non-conformities in 90 days
Challenge
An internal audit identified seven CDM 2015 nonconformities across three live projects, with an HSE inspection scheduled the following quarter.
Approach
We deployed two consultants part-time across the projects. Reissued pre-construction information, rewrote construction phase plans against current scope, retrained Principal Designer touch points, and ran a mock HSE inspection two weeks before the real one.
Outcome
All seven NCRs closed within 60 days. HSE inspection completed with verbal commendation and no enforcement action. Approach rolled out across the contractor's London framework.